Construction of a wind farm in the German waters of the Baltic Sea, set to supply power for 400,000 homes, is ahead of schedule, the head company said. German utility E.ON said Wednesday that construction of its Arkona wind farm is moving into its second phase a bit early, with the 60 foundations already set in place for their Siemens turbines. The 60-turbine wind farm is set about 22 miles off the coast of Germany. Construction of the actual turbines is under way and the offshore infrastructure is set for cabling and connection to the substation. The company deployed the 60 so-called monopiles in September. Foundations for a common substation were installed the month prior and the entire project could start […]