French nuclear output fell below 41 GW Wednesday morning, with operator EDF listing three unplanned short-term outages with a combined 3 GW capacity, according to grid operator RTE. Receive daily email alerts, subscriber notes & personalize your experience. Register Now 1.3 GW Belleville-2 in unplanned shutdown overnight 0.9 GW Gravelines-6 also taken offline overnight 0.9 GW Tricastin-2 restart attempt delayed again The 1.3 GW Belleville-2 reactor was shut down late Tuesday night after three measuring devices were found to be malfunctioning, EDF said in a brief statement, with the unit currently expected to return overnight into Thursday. The 0.9 GW Gravelines-6 reactor was also taken offline in an unplanned outage overnight and is expected to return at 5 am local time Friday, according to EDF Transparency. The return of the 0.9 GW Tricastin-2 unit, offline since June for various reasons, was postponed again, with EDF Transparency now […]